City of Torrance logo

Pacific Coast Highway at Hawthorne Boulevard

Intersection Improvement Project

Phase 2 and Phase 3 work continues through October 2022

Posted September 20, 2022

The City’s contractor, Griffith Company, will continue to perform work at the intersection of Pacific Coast Highway and Hawthorne Boulevard per the exhibit below through October 2022. Significant traffic impacts are expected. Please use alternate routes, when possible.

Phase 2 work (in green) generally consists of new sidewalk, curb and gutter, handicap curb access ramps, traffic signal improvements, and concrete pavement on the north side of Pacific Coast Highway. Phase 3 work (in yellow) generally consists of placement of concrete pavement on the center lanes of PCH.